KAFD - Minor & Main Works to Complete for Parcels 1.08 & 2.07 – Stage 1

Location:

Riyadh, K.S.A.

Architect/Consultant:

Saudi Arabian Parson Co. Ltd.

Owner:

KAFD Development and Managemet Co. (KAFDCo)

Designer:

Various Designers

Awarded:

March, 2019

Contract Value:

SAR 36 million / USD$9.6 million


General description:

  • Dilapidate the discontinued constructed Parcels 1.08 and 2.07 (2 Parcels = 4 Towers) at KAFD.


The project also include:

  • HSE MAKE SAFE:
  • Taking all measures necessary to ensure safe access and building occupancy.
  • Dismantling of unneeded equipment, as well as housekeeping and cleaning of both parcels.
  • DILAPIDATION SURVEY:
  • Prepare status surveys and assessments of all Architectural and MEP installations and systems to the buildings and skywalks. Including, but not limited to:
  • Visual surveys.
  • Simple & Specialist tests and measurements.
  • Internal examination of plant and equipment.
  • Analysis of supporting data.